當然最好現在谘詢一下律師。90天不是你的期限,是他們加mechanics lien的期限。我認為他們必須在六個月之內來告你,否則Mechanics lien在停工後六個月自動作廢
Enforcing a Mechanic’s Lien
Contractors, subcontractors or suppliers with a properly perfected lien, called “lienholders,” must enforce the lien by foreclosure. To do this, the lienholder must bring suit to foreclose the lien and file a notice of pendency of the action within six months after the last day labor was furnished or materials were provided. S.C. Code Ann. § 29-5-120.