這種壓力常見。從PM的角度說兩點。。。

來源: 2012-02-02 17:26:32 [博客] [舊帖] [給我悄悄話] 本文已被閱讀:

(1)各司其責(R&R): 你幹的是班長的活,就不要操軍長的心。你的責任沒那麽大。

(2)時間管理(time management):

Network change and software testing after the change are sequential events (finish-to-start relationship).

Time to finish testing = X (network change completion milestone) + Y (time needed to test in new env.)

Bottom line:

It is a problem. However, you are not the cause. You are the symptom. Do help resolve the problem. Don't lose sleep over it. You are not responsible for other people's delays and poor planning.